Weaver to Wavertree Resignalling Project

22 miles of track resignalling, split into 2 phases. As part of the project Readypower was awarded a design and build contract for the signalling sub structures and superstructures:

Weaver to Wavertree Resignalling Project

  • 3 No. Four Track Gantries
  • 3 No. Twin Track Cantilevers
  • 29 No. Traditional Signal Structures
  • 38 No. Lightweight Signals (Foundations only)
  • 9 No. LOC Stagings
  • 4 No. OFF Indicator Brackets on Station Platforms
  • 1 No. Retrofit to an existing signal to enable the installation of an additional
    signal head
  • Removal of redundant signalling assets

Design Phase

Readypower managed the design through the optioneering stages to sign off at AFC. As the Project was multi-disciplinary, Readypower Engineers were embedded in the project, collaborating with other discipline Engineers, including Network Rail Project Engineers, to ensure the designs were fully integrated and compliant to National Rail standards.

 

Construction Phase

Both phases were delivered successfully in time for commissioning. This success was down to critical path planning and relentless driving of the programme. The main issue was the limited and varied access to the infrastructure. Missed opportunities, or incomplete works having a huge impact on the tight programme. Foundations were a mixture of Driven CHS piles, rock anchor with grillage, Cast in situ reinforced concrete gravity pads and pre cast reinforced concrete gravity pads. The internal capability and capacity to deliver all solutions, afforded tight
control over programme, quality, safety and budget. Readypower Rail Services supplied Road Rail plant, piling rigs, MEWPS and cranes to facilitate foundation construction, structure erection and structure decommissioning.

 

The way you and your team
supported some late challenges
following several significant test logs
raised by Siemens was supported
superbly by your team and effectively
and safely carried out. Once again
this proved how well our teams work
together and between our teams
undertook these additional works
within a matter of days.